The Challenge
Soho Apartments had non-compliant ACP cladding across its facade. In June 2023, City of Sydney Council issued a Fire Safety Order requiring the Owners Corporation (SP70319) to rectify the cladding. The building remained fully occupied throughout, and the FSO imposed a legal compliance deadline with escalating enforcement risk for all lot owners.
The Solution
Wardell Remedial was engaged in December 2024 to deliver the full replacement package. Working from regulated design drawings by facade engineer Fahrenheit Global, Wardell managed construction delivery, all council liaison and permit applications, scaffolding design and certification, and NSW Planning Portal submissions. The ACP was replaced with 9mm Cemintel CFC cladding — a non-combustible, NCC-compliant system — installed with top hat framing, vapour barrier, mechanical fixings and all flashings. A Dulux-approved facade coating was applied to restore the building’s original appearance.
Key delivery elements:
A-Type gantry hoarding maintaining unrestricted resident access throughout works
Footpath occupation permit managed with City of Sydney Council
Regulated design, compliance declarations and as-built drawings uploaded to NSW Planning Portal
Cladding sample approval, site management procedures and installation certificate submitted to council
Direct liaison with Fahrenheit Global to resolve design RFIs during construction
Key Metrics
PROJECT VALUE
$260K
PROGRAMME
10
Weeks
COMPLIANCE
City of Sydney FSO
Why Wardell Remedial
Cladding rectification under a Council Fire Safety Order demands a builder who can manage regulatory submissions, coordinate with facade engineers, navigate council permitting and deliver quality construction on an occupied building — simultaneously. Wardell Remedial is registered under the Design and Building Practitioners Act 2020 and handles the full compliance pathway in-house, from regulated design coordination through to NSW Planning Portal sign-off.